Plans to demolish eyesore and build 70 homes given thumbs-up

Plans for an eyesore to be knocked down and replaced with 70 homes have been given the thumbs-up despite locals' opposition. The project for R&J Supplies ...


Plans to demolish eyesore and build 70 homes in Hayle given thumbs-up by Cornwall Council

Residents had previously opposed to the scheme

This is what the development could look like (Image: Planning application)

Plans for an eyesore to be knocked down and replaced with 70 homes have been given the thumbs-up despite locals’ opposition.

The project for R&J Supplies on Copper Terrace, Hayle, to be demolished was submitted to Cornwall Council three years ago.

Kemmann-Lane & Associates, on behalf of R Maskell Limited, sought planning permission to get rid of the disused factory and turn it into a residential site.

This month, Cornwall Council’s planning committee gave the project the green light, despite residents’ negative reaction.

The plans include 70 homes comprising one and two-bedroom flats, two two-bedroom houses and one four-bedroom house.

The developers wrote: “These industrial buildings are in poor condition and, to put it mildly, are an eyesore crying out for removal and sensitive replacement.

Developers described the building as 'an eyesore crying out for removal' (Image: Google)

“The redevelopment, which is in accordance with Local Plan policy, cannot take place without clearance of the site.”

The warehouse is 3,600sqm. The scheme will also include improvement works to the access road, landscaping, cycle and bin storage and parking provision.

In all, the developers want to increase the number of spaces on site to 89.

After the application was submitted in November 2015, locals took to Cornwall Council’s planning portal to show their opposition to the plans.

In all, eleven out of 12 comments submitted by members of the public were negative.

Ben Cwilewicz fully opposed to the plans, writing: “I believe that 3 houses and 67 flats can be seen as nothing but over development.

“This is Hayle, there is no need for this density of development.”

James Buchanan commented: “In principle the inevitable regeneration of this site is acceptable.
“However, with Hayle increasingly congested particularly through the summer months the need for an additional junction on/off the A30 at the B3302 is now critical. It should be a condition of this and future housing schemes that a contribution is made to fund a new junction,
“It should have been built when Asda was developed and no future large developments in the area should go ahead until this junction is in place.”

Tony Riggall said: “The proposed elevations of Block C in the plan section CC will be built in front of our home making it darker and will be overbearing giving us no privacy, especially with a balcony directly opposite us. From every window in the front of our property we would now be looking at the development.

“The proposed development lies within a conservation area and between listed buildings. Surely blocks of flats of 5 storey plus 50 degree pitch roofs in height cannot be considered as being in keeping with the surrounding area. Will this not also affect the setting of the listed buildings at each end?

“Surely a 3 storey building plus a 30 degree roof is more in keeping with Hayle, would we be right in saying a previous application for a lower development was withdrawn by the applicant at appeal, which begs the question why are they now applying for a much larger one in the light of that?

“The existing warehouse does need replacing and would be much welcomed but a development of this height and size is not the way forward!”

Cornwall Council gave conditional approval to the developers, saying:

“No demolition/development shall take place/commence until a programme of archaeological work including a Written Scheme of Investigation has been submitted to and approved by the local planning authority in writing.

“The scheme shall include an assessment of significance and research questions, and: 1. The programme and methodology of site investigation and recording, 2. The programme for post investigation assessment, 3. Provision to be made for analysis of the site investigation and recording, 4. Provision to be made for publication and dissemination of the analysis and records of the site investigation, 5. Provision to be made for archive deposition of the analysis and records of the site investigation, and 6. Nomination of a competent person or persons/organisation to undertake the works set out within the Written Scheme of Investigation.

“No demolition/development shall take place other than in accordance with the Written Scheme of Investigation approved under condition (A).

“The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under condition (A) and the provision made for analysis, publication and dissemination of results and archive deposition has been secured.

“The archaeological recording condition will normally only be discharged when all elements of the WSI including on site works, analysis, report, publication (where applicable) and archive work has been completed.”

For the full list of conditions, click here .

 

Site Plan proposed | PA15/10513 | Demolition of existing warehouse type building comprising 3,600 square metres of floorspace and the erection of a 70 unit residential development comprising 2no. 2-bed houses, 1no. 4-bed house, 10no one-bed flats and 57no
Computer generated view | PA15/10513 | Demolition of existing warehouse type building comprising 3,600 square metres of floorspace and the erection of a 70 unit residential development comprising 2no. 2-bed houses, 1no. 4-bed house, 10no one-bed flats and

Book page

TitleCreated
2026-EXTENDED-17th April 2026 to 22nd April- Resurfacing Steamers Hill; Hatchs Hill; Angarrack Lane | 1 Apr 07:30 - 17 Apr 23:59 8 hours 19 sec agoBook page
2026-April-POSTPONED-planned improvements i.e. install footpath, paint double yellow lines junction Grist Lane Hatchs Hill 3 days 21 hours agoBook page
2026 - Resurfacing Steamers Hill; Hatchs Hill; Angarrack Lane | 1 Apr 07:30 - 17 Apr 23:59 2 weeks 1 day agoBook page
250330; Closure order:30 Mar-17 Apr 2026; 07:30-17:00; Clearway Parking Zone; Hatchs Hill, Steamers Hill and Angarrack Lane 3 weeks 3 days agoBook page
Traffic/Roads - Marsh/Grist Lane - Traffic counts 2019 onwards 15 weeks 14 hours agoBook page
Approved with conditions | PA25/07094 | First floor extension over existing garage to create Art studio with guest bedroom... 19 weeks 3 days agoBook page
PA25/07094 | First floor extension over existing garage to create Art studio with guest bedroom, covered parking area below | As 20 weeks 2 days agoBook page
251027 | 20mph Monitoring—Hayle & St Ives Speed Data; Phase 3a-May-Jun 24 v Sep-Oct 24; Steamers Hill; Gwinear;Carbis;Nancledra 24 weeks 2 days agoBook page
PA25/07184 | Retention of 4no. existing holiday pods, swimming pool, incidental building, extended driveway and annexe converted 24 weeks 5 days agoBook page
251009 | Stark reality of life in Cornwall revealed through 2025 Vital Signs Report 26 weeks 6 days agoBook page
251010 | Cornwall backs 20mph rollout; St Austell's the only town to reject the plans 26 weeks 6 days agoBook page
250930 | Cornwall’s 20 mph speed limits have made the roads much safer 28 weeks 2 days agoBook page

Jeremy Rowe LD | Egloshayle, St Breock, St Ervan, St Eval, St Issey, St Mabyn & St Tudy