140904 | Council meeting - Representatives from ASDA and Simon Humphrey from Bowmer & Kirkland were present

Via http://hayletowncouncil.net/documents/4Sept2014DraftMinutes.pdf

Representatives from ASDA and Simon Humphrey from Bowmer & Kirkland were present.

Doug Wilson from ASDA reported that there had been a successful meeting on site regarding the heritage trail. He said that he would welcome views on the store, especially the cladding. He said that the amended proposal for signage on the building was unique and bespoke for Hayle and had incorporated feedback from Councillors. He added that recruitment for store employees had started and that 24 November 2014 was the target opening date.

Simon Humphrey reported that good progress had been made, especially over the previous two to three months, and that all the remaining work had been programmed in. He was proud of the achievement regarding the repair of the bridge. The sluicegates were now in and he invited everyone to view the site at 9.30 - 10.30am on Saturday and Sunday. He said that the breakthrough into Carnsew Pool would be made in two weeks’ time, for the first time in 40 years. He planned to arrange a litter pick and hoped to get schools involved; Councillors were also welcome to participate. It was suggested to him that the RSPB and Save Our Sands might also be able to help.

Regarding the secondary sluices it was reported that it was hoped they would be ready in January. They would also be hydraulically operated, but could be operated manually if necessary.

Simon Humphrey also told the meeting that temporary traffic lights would be re-installed on Carnsew Road the following week. In answer to questions Doug Wilson said that he could introduce the new ASDA store manager at the next Full Council meeting. He told Members that ASDA always looks to work with local employees, but that they have to operate within certain constraints. He said that he would monitor the location that employees came from, but he was sure that some would be employed from the local area. He informed everyone that initial job applications were all done online and that if a candidate failed at this stage their application would not go any further.

Book page

TitleCreated
2026-EXTENDED-17th April 2026 to 22nd April- Resurfacing Steamers Hill; Hatchs Hill; Angarrack Lane | 1 Apr 07:30 - 17 Apr 23:59 6 hours 3 min agoBook page
2026-April-POSTPONED-planned improvements i.e. install footpath, paint double yellow lines junction Grist Lane Hatchs Hill 3 days 19 hours agoBook page
2026 - Resurfacing Steamers Hill; Hatchs Hill; Angarrack Lane | 1 Apr 07:30 - 17 Apr 23:59 2 weeks 1 day agoBook page
250330; Closure order:30 Mar-17 Apr 2026; 07:30-17:00; Clearway Parking Zone; Hatchs Hill, Steamers Hill and Angarrack Lane 3 weeks 3 days agoBook page
Traffic/Roads - Marsh/Grist Lane - Traffic counts 2019 onwards 15 weeks 12 hours agoBook page
Approved with conditions | PA25/07094 | First floor extension over existing garage to create Art studio with guest bedroom... 19 weeks 3 days agoBook page
PA25/07094 | First floor extension over existing garage to create Art studio with guest bedroom, covered parking area below | As 20 weeks 2 days agoBook page
251027 | 20mph Monitoring—Hayle & St Ives Speed Data; Phase 3a-May-Jun 24 v Sep-Oct 24; Steamers Hill; Gwinear;Carbis;Nancledra 24 weeks 2 days agoBook page
PA25/07184 | Retention of 4no. existing holiday pods, swimming pool, incidental building, extended driveway and annexe converted 24 weeks 5 days agoBook page
251009 | Stark reality of life in Cornwall revealed through 2025 Vital Signs Report 26 weeks 6 days agoBook page
251010 | Cornwall backs 20mph rollout; St Austell's the only town to reject the plans 26 weeks 6 days agoBook page
250930 | Cornwall’s 20 mph speed limits have made the roads much safer 28 weeks 2 days agoBook page