DELEGATED ENFORCEMENT REPORT

Reference No:

PA14/02920, Section 106 Agreement dated 27 July 2016

Site Address:

Hayle Rugby Club, 10 Marsh Lane, Hayle TR27 5HX

Alleged Breach:

Breach of Section 106 Section 106 Agreement dated 27 July 2016, clause 4.3 - To pay the Council’s Planning Administration fee of £3750.00 on completion of this Deed.

Interested Parties:

Hayle Rugby Football Club, Memorial Park, Marsh Lane, Hayle TR27 4PS

Site Description:

Outline application with some matters reserved for proposed development of up to 15,539 sq.m. (gross) retail development (A1/A3), associated infrastructure, access arrangements, servicing, parking and landscaping.

Description of the Breach of Planning Control:

Breach of Section 106 Section 106 Agreement dated 27 July 2016, clause 4.3 - To pay the Council’s Planning Administration fee of £3750.00 on completion of this Deed.

Conclusion & Recommendation

The company secretary at Hayle Rugby Football Club Ltd was issued with a 30 day Notice that Payment was Due letter on the 02 September 2016 and then a 7 day reminder on the 29 May 2018. There is an e-mail confirming that the club will not be paying the fee; please see below:

Further to your letter of the 30th April to the Secretary of Hayle Rugby Club I would confirm that all communication in this regard should come to the writer.

The current position is that it is highly likely given the changing economic and retail climate in the UK that a further application will be submitted with regard to this site to better reflect the changes in the retailing sector that have occurred in the last two years. It is unlikely that the current scheme will be implemented in its existing form.

Therefore the Planning Administration in respect of this consent will not occur. That being the case it is not appropriate to charge for something that is not going to happen. Should circumstances change which is highly unlikely then of course we will notify you but as it stands there is nothing for the Council to administrate.

Yours faithfully

Richard Walker

The Council could pursue this matter further, however this course of action would not be the best use of resources or in the public interest when considering the development has not commenced. Should the development commence within the timescale of the planning permission then the planning administration fee will be pursued.

Signed: image001.jpg@01D3B6CA.071BAE60 Dated: 09.11.2018

Development Officer

(Section 106 Obligations)

Signed: Dated: 9/11/2018

Group Leader


 

 

a

Book page

TitleCreated
190321 | Closure | Commercial Road weekdays 25 Mar to 5 Apr 3 days 12 hours agoBook page
190321 | Closure | Roseworthy Hill 18 Mar to Jun 07:40 to 17:00 3 days 12 hours agoBook page
190314 | Police hunt driver after hit and run crash on A30 Loggans Moor roundabout | Google News 1 week 3 days agoBook page
190314 | Family who lost their GoPro camera while surfing are reunited with it - 10 MONTHS later | Google News 1 week 3 days agoBook page
Superseded | PA19/00868 | PA19/00868 | Application for discharge of Condition 5 (boundary treatment) PA15/01953 - 12 Back Lane 1 week 3 days agoBook page
Approved with conditions 190311 | PA19/00229 | Proposed Garden Room , new windows doors widening access bridge - 15 Riverside 1 week 5 days agoBook page
190213 | Plan for regeneration of Hayle Harbour will see new homes and jobs for people in Cornwall - Cornwall Council 1 week 6 days agoBook page
190213 | Call for council to take on whole Hayle Harbour redevelopment if it's ever going to happen - Cornwall Live 1 week 6 days agoBook page
Amended plans PA18/04577 | Application for approval of reserved matters (access, appearance, landscaping, layout and scale) purs 1 week 6 days agoBook page
190301 | PA18/05585 and Listed Building Consent PA18/05586 Loggans Mill, Melyn Close, Loggans, Hayle (amended plans) 1 week 6 days agoBook page
181121 | Alleged Breach of Section 106 Section 106 Agreement dated 27 July 2016, clause 4.3 - To pay the Council’s Planning Admi 1 week 6 days agoBook page
PA19/02040 | EIA screening request for highway improvements to Loggans Moor roundabout - Hayle A30 Loggans Moor Roundabout 1 week 6 days agoBook page

tags for 181121 | Alleged Breach of Section 106 Section 106 Agreement dated 27 July 2016, clause 4.3 - To pay the Council’s Planning Admi